Sl No. | Name of Project | Estimated Capacity | Target | Target |
---|---|---|---|---|
1 | 220kV D/C Mori – Dehradun Line (232 Ckm) | For power evacuation of 60 MW Naitwar Mori (M/s SJVN) & other HEP in Yamuna Valley |
491.16/311.24 | 1. Committee constituted on Chairmanship of independent Director Sh. R. P. Sasmal to clear technical feasibility. 2. Alternate Route (if any). 3. Board/ADB to clear tendering process 4. Tendering to be done. |
2 | Khandukhal (Srinagar) – Rampura (Kashipur) 400 KV D/C line (380 Ckm) |
Required for evacuation of power from Singoli Bhatwari HEP (3x33MW), Tapovan Vishnugad HEP(4x130MW) and Vishnugad Pipalkoti HEP (4x111MW) beyond Srinagar. |
1099.00/877.89 | 1. Committee constituted on Chairmanship of independent Director Sh. R. P. Sasmal to clear technical feasibility. 2. Alternate Route (if any). 3. Tendering to be done |
3 | 132/33 kV GIS S/s Lohaghat (2x40MVA) | For improvement of power supply in Champawat District. | 93.16/57.80 | Tendering is in progress, Bid submission date is 01.09.2020 |
4 | 220/33kV GIS S/s Selaqui Dehradun 2X50MVA) | For improvement of power supply in Selaqui Industrial area | 82.71/71.52 | Tendering is in progress, Bid submission date extended till 08.09.2020 |
5 | LILO of 220 kV S/C of Khodri-Jhajra Line at proposed 220 kV Selaqui, Dehradun with underground cable (0.8KM) |
For improvement of power supply in Selaqui Industrial area | 36.29/31.55 | Price Bid opened |
6 | 220/33 kV Brahamwari S/s (6x10 MVA) & Associate Lines (15 Ckm) | Required for evacuation of power from M/s UJVNL Generators & UPCL System Strengthening. |
222.35/139.04 | Investment Approval is in process. |
7 | OPGW work on 400 kV DC Vishnugad-Pipalkoti Line (18 Km) & LILO of 400 kV D/C Vishnuprayag-Muzaffarnagar line at Pipalkoti S/s (4 Km) & 400 kV S/s Srinagar to M/s GVK Power House |
Required for alternative evacuation of power from Singoli Bhatwari HEP (3x33MW), Tapovan Vishnugad HEP (4x130MW) and Vishnugad Pipalkoti HEP (4x111MW) beyond Srinagar. |
– | DPR under preparation. |